2011-12-08
|
Inauguration of the Liotech plant
|
2011-10-07
|
Startup of integrated testing of the plant production equipment.
|
2011-07-12
|
Chinese and Russian specialists embarked on production equipment installation. Started mounting of manufacturing equipment
|
2011-05-30
|
Shipment of equipment from China to the plant in Novosibirsk began.
|
2011-03-30
|
|
2011-03-25
|
The State Commission accepted into service the lithium-ion accumulators plant building.
|
2010-09-28
|
|
2010-07-14
|
|
2010-04-28
|
Liotech Ltd. and Ńhinese company Thunder Sky signed a contract for delivery of processing equipment for the production of lithium-ion accumulators
|
2010-04-20
|
|
2010-02-03
|
Li-ion Technologies Limited company (Liotech Ltd.) was registered.
|
2009-12-22
|
RUSNANO’s supervisory board approved participation of the Corporation in the project on the first Russian production of modern lithium-ion accumulators.
|